After completing the initial 'rough' engineering I received this estimate from the local power company:
This is the 'rough' estimate simple to hook-up to the grid. And mind you my property isn't very far:
I asked if dowgrading my power requirements by half would do anything to change the financial picture, the answer was no:
So, I'm left with a choice. Pay $30k to hookup to the grid and then pay for electrical and billing service charges every month regardless of use . Oh, BTW: I'm not making that up, those are real charges levied by the power company.
OR... I can suck it up and create my own microgrid. And that's what I've decided to do.